Floods halt 55MW power generation in Taplejung-Panchthar corridor

From Kathmandu Post · () English

Summarized by DistantNews. Read the original for the full story.

At a glance

News Named sources Outcome reported
  • Floods in Nepal's Taplejung and Panchthar districts damaged four hydropower projects, halting 55 megawatts of power generation.
  • The Kabeli B-1 project and three others on the Kabeli and Indrawati rivers suspended production after floodwaters damaged their structures and intakes.
  • The disruption affects electricity supply connected to the Amarpur substation in Panchthar.

Heavy rainfall and flooding in Nepal's Taplejung and Panchthar districts have brought 55 megawatts of power generation to a standstill. The deluge, occurring on Friday night, damaged hydropower projects situated along the Kabeli and Indrawati rivers, forcing a complete halt in production.

Four projects, including the 25MW Kabeli B-1 hydropower project operated by Arun Kabeli Power Limited, experienced disruptions. Floodwaters damaged structures and intakes, leading to accumulations of stones, mud, silt, and logs that blocked operations. Lekharaj Neupane, an employee at Arun Kabeli Power Limited, confirmed the damage to the project's intake and other structures.

floods damaged the intake and other structures of the project. He said stones, mud, silt and logs carried by the floodwaters had piled up at the dam and intake areas, halting production.

· Lekharaj NeupaneAn employee at Arun Kabeli Power Limited described the damage to the Kabeli B-1 project.

Similarly, the 9.9MW Iwa Khola project by Ridi Hydropower Limited and the 9.7MW project by Iwa Hydropower Limited on the Indrawati river also suspended generation. Mausam Seyling, an employee at Iwa Hydropower Limited, reported that floodwaters damaged the intake area, pipelines, and powerhouse structures of their project. The electricity from these affected projects is channeled to the Amarpur substation in Panchthar.

floodwaters damaged the intake area, pipelines and powerhouse structures of the project.

· Mausam SeylingAn employee at Iwa Hydropower Limited explained the impact of the floods on their project.