Kathmandu Power Supply Disrupted After Two Transmission Circuits Trip
๐Ÿ‡ณ๐Ÿ‡ต Nepal /Energy & Infrastructure

Kathmandu Power Supply Disrupted After Two Transmission Circuits Trip

From OnlineKhabar English · () English

Translated from English and summarized by DistantNews. Read the original for the full story.

At a glance

News Sources not specified Outcome reported
  • Electricity supply in Kathmandu and central Nepal was disrupted on Friday due to issues with the Khapti-Dhalkebar 220 kV transmission line.
  • Problems occurred in both circuits of this line, coinciding with a scheduled shutdown of another transmission line.
  • The Nepal Electricity Authority (NEA) reported the disruption, noting that the Hetauda-Dhalkebar 400 kV line is currently under construction.

Kathmandu and surrounding areas in central Nepal experienced significant power outages on Friday. The disruption stemmed from simultaneous problems affecting key electricity transmission infrastructure.

Specifically, both circuits of the Khapti-Dhalkebar 220 kV transmission line malfunctioned. This occurred while another critical transmission line was already undergoing a scheduled shutdown for maintenance or upgrades. The combined impact of these issues led to a widespread loss of electricity supply.

The Nepal Electricity Authority (NEA) confirmed the situation, attributing the outage to the transmission line problems. The NEA also noted that the Hetauda-Dhalkebar 400 kV transmission line is currently in the process of construction, indicating ongoing development in the region's power infrastructure.

About this summary

Originally published by OnlineKhabar English in English. Translated, summarized, and contextualized automatically by DistantNews, with a note on how the source frames the story. Not individually reviewed before publishing. How this works.