Mexico City-Querétaro Train to Arrive by Mid-2027, Government Projects
Translated from Spanish and summarized by DistantNews. Read the original for the full story.
At a glance
- Mexico's government expects the first trains for the Mexico City-Querétaro high-speed rail line to arrive by mid-2027.
- The project involves acquiring 15 electric trains for the AlFA a Pachuca service and 47 diesel-electric trains for northern routes.
- Significant progress is reported on railway construction, with plans to build over 2,300 kilometers of track during the current administration.
The Mexican government, through the Regulatory Agency for Railway Transport (ARTF), has provided a significant update on the ambitious high-speed rail projects connecting key cities. The anticipated arrival of the first trains for the Mexico City-Querétaro and Saltillo-Nuevo Laredo routes by mid-2027 signals tangible progress in modernizing the nation's transportation infrastructure. This development is crucial for enhancing connectivity and stimulating economic activity across these vital corridors.
The first train for the Mexico City - Querétaro route will arrive at the end of the first half of 2027, and for the Saltillo - Nuevo Laredo section, in the second half of 2027.
ARTF head Andrés Lajous Loaeza detailed the procurement of 15 electric trains for the AlFA a Pachuca service and 47 diesel-electric trains for the northern phase one routes. The ongoing validation of executive projects and the imminent start of manufacturing for these trains underscore the government's commitment to these large-scale endeavors. The sheer scale of the planned railway network, with a projected 2,377 kilometers of new track to be laid during the current administration, speaks to a vision of a more integrated and efficient Mexico.
We are already in the final validation of the executive project for the trains, the supply of critical initial consumables, and we will begin manufacturing in June, meaning in a couple of weeks we will be starting the manufacturing of the 47 diesel-electric trains.
While international coverage might focus on the technological aspects or the financial investment, from a Mexican perspective, these projects represent more than just infrastructure. They embody a national aspiration for development, a commitment to reducing travel times, and a strategy to boost regional economies. The progress on the Querétaro-Irapuato and Saltillo-Monterrey Nuevo Laredo lines, despite being in early stages, shows a determined push forward. This is about building the future of mobility in Mexico, connecting our people and our industries in ways previously unimagined, and solidifying our position as a key player in North American logistics.
The Querétaro - Irapuato route project, which will be 108.2 kilometers long, is currently in the piling phase, with 15 active work fronts over 48 kilometers, representing 15% physical progress.
Originally published by El Universal in Spanish. Translated, summarized, and contextualized automatically by DistantNews, with a note on how the source frames the story. Not individually reviewed before publishing. How this works.