Nepal prioritizes stalled national pride projects: Fast Track, railways
Translated from English and summarized by DistantNews. Read the original for the full story.
At a glance
- The Nepali government has prioritized the completion of the Kathmandu–Terai/Madhesh Fast Track and associated infrastructure, despite significant delays.
- The Fast Track project, initiated in 2017 and entering the contract phase in 2021, has achieved 45.16 percent physical progress, with delays attributed to procurement and contracting issues.
- The government also reaffirmed its commitment to the East-West Electric Railway and plans to study investment models for international rail corridors, alongside accelerating national road network expansion.
The Nepali government has once again pledged to prioritize stalled national pride projects, including the Kathmandu–Terai/Madhesh Fast Track and the East-West Electric Railway. While these projects have been long-standing promises, their slow progress has been a source of frustration for the public. The Fast Track, eight years into construction, has only reached 45.16 percent completion, with the Nepali Army citing delays in procurement and contracting as major impediments.
The government will adopt measures to expedite completion of the Fast Track and ensure faster progress on associated infrastructure links, positioning it again as a key national priority project.
The East-West Electric Railway, a project consistently featured in election manifestos for decades, has also seen limited progress despite substantial investment. Obstacles such as land compensation for affected households continue to hinder construction. The government's renewed commitment, however, includes studying investment models for crucial international rail corridors like the Kerung–Kathmandu and Raxaul–Kathmandu railways, aiming to bolster regional connectivity.
Construction of the East-West Railway will continue, while investment models will be studied for two major international corridors: Kerung–Kathmandu and Raxaul–Kathmandu railways.
To address these persistent delays, the government plans to strengthen the Prime Minister’s Delivery Unit and implement a mission-based model. An improved contract system and effective engineering standards are also proposed to ensure timely completion of large-scale projects. The inclusion of these stalled projects as key national priorities signals a potential shift in focus, but the effectiveness of these measures remains to be seen, given the history of unmet deadlines and bureaucratic hurdles.
To accelerate infrastructure development, the Prime Minister’s Delivery Unit will be strengthened and implemented in a mission-based model.
From a Nepali perspective, these infrastructure projects are not merely about transportation; they represent national ambition, economic development, and strategic positioning within the region. The delays reflect deeper issues within governance and project execution, making the government's renewed emphasis a critical test of its ability to deliver on long-promised development goals. The success of these projects is vital for national pride and economic upliftment.
An improved contract system and effective engineering standards will be ensured to complete large projects on time.