- Mexico City officials said construction has reached the foundation stage at the San Nicolás station on the Tlalpan-Coyoacán Line 4 Cablebús.
- Crews are working on foundation piles and grade beams, with five of the planned 24 piles currently being drilled.
- The foundation work will support the station structure and allow construction to move toward the next stage.
Construction of the San Nicolás station on Mexico City’s Line 4 Cablebús is moving ahead with foundation work in the Pedregal de San Nicolás 4th Section neighborhood of the Tlalpan borough.
The city’s Secretariat of Works and Services said crews are installing the infrastructure needed to support the terminal. The current work focuses on drilling foundation piles and building grade beams, which provide stability for the station.
The project calls for 24 foundation piles. Five are currently being drilled with specialized machinery. Officials said these initial works will allow the station structure to rise later in the construction process.
“The Cablebús will transform the urban environment and make a new connection possible for communities in the south of the city,” the secretariat said.
The Cablebús will transform the urban environment and make a new connection possible for communities in the south of the city.
Originally published by El Universal in Spanish. Translated, summarized, and contextualized automatically by DistantNews, with a note on how the source frames the story. Not individually reviewed before publishing. How this works.
Image: Especial.