Tomašević jokes about long-delayed Špansko pool opening and explains the holdup
Translated from Croatian and summarized by DistantNews. Read the original for the full story.
At a glance
- Zagreb Mayor Tomislav Tomašević said the long-awaited Špansko swimming pool should open next week after receiving its operating permit.
- He attributed delays to the complex permits, inspections and technical procedures required for a pool project.
- Tomašević said the city will impose contractual penalties if expert supervision finds the contractor responsible, but not if delays resulted from force majeure.
The Špansko swimming pool has finally received its operating permit, but Zagreb Mayor Tomislav Tomašević kept the exact opening date under wraps, at least as a joke.
“ We have an exact date, but I won’t say it. I’m joking. It should open next week. I hope to see you next week to open the pool,” Tomašević said when asked when residents would finally be able to use the long-awaited facility and who would answer for the missed deadlines.
He said the delay reflected the complexity of building a swimming pool. Roads, buildings, kindergartens and schools follow familiar procedures for operating permits and technical inspections, he explained, while Zagreb builds pools much less often. A stadium may be built once in 50 years and a pool once in 20, he said, making these projects more complex and requiring different permits, inspections and technical reviews.
We have an exact date, but I won’t say it. I’m joking. It should open next week. I hope to see you next week to open the pool.
Tomašević said unforeseen complications can arise during technologically demanding projects and push back deadlines. Asked who would be held responsible, he said the expert supervisor hired by the city through a public procurement process would determine whether the contractor caused the delay.
If the supervisor assigns responsibility to the contractor, the city will charge contractual penalties. If the delay resulted from force majeure, the city cannot impose them, Tomašević said.
If the supervisor defines it as the contractor’s fault, then we charge penalties. If it turns out to be force majeure, then we cannot charge penalties.
Originally published by Večernji List in Croatian. Translated, summarized, and contextualized automatically by DistantNews, with a note on how the source frames the story. Not individually reviewed before publishing. How this works.