  • Electricity generation at unit-1 of the Barapukuria Thermal Power Plant resumed after a day-long shutdown.
  • A mechanical glitch affecting a service water pump was fixed, restoring about 50-55 megawatts to the national grid.
  • The plant requires an overhaul of unit-1, which was last conducted in January 2020, to ensure consistent power generation.

Power generation at unit-1 of the Barapukuria Thermal Power Plant in Dinajpur has restarted after a one-day halt. The plant's chief engineer, Mohammad Abu Bakar Siddique, confirmed that power generation resumed at 9:00 AM today after a mechanical issue was resolved. This has added approximately 50-55 megawatts to the national grid.

The unit had previously suspended operations on Friday morning due to a malfunctioning service water pump. This is not the first recent interruption; the same unit also stopped generating power on July 31 due to mechanical failure, resuming service on August 2 after repairs.

power generation resumed at 9:00am today after a mechanical glitch was fixed, adding around 50-55 megawatts (MW) of electricity to the national grid.

โ€” Mohammad Abu Bakar SiddiqueThe chief engineer of the Barapukuria Thermal Power Plant confirmed the resumption of power generation.

Currently, unit-1 and unit-3 are supplying electricity to the national grid, contributing around 170 MW. Unit-2 has been out of operation since 2020. The plant's total generation capacity is 525 MW, with unit-1 and unit-2 each capable of 125 MW, and unit-3 having a capacity of 275 MW.

Siddique explained that the frequent shutdowns are partly due to the need for an overhaul of unit-1. The last overhaul was performed in January 2020, and such maintenance is typically required every five years to ensure uninterrupted power generation.

An overhaul is required after five years to ensure uninterrupted power generation.

โ€” Mohammad Abu Bakar SiddiqueThe chief engineer explained the reason for the plant's frequent shutdowns.