DistantNews
Support us
Long Thanh Airport Project Faces Worker Shortage Amidst Push for 2026 Opening
๐Ÿ‡ป๐Ÿ‡ณ Vietnam /Energy & Infrastructure

Long Thanh Airport Project Faces Worker Shortage Amidst Push for 2026 Opening

From Tuแป•i Trแบป · () Vietnamese

Translated from Vietnamese, summarized and contextualized by DistantNews.

At a glance

News Sources not specified Ongoing story
  • The Long Thanh International Airport project in Vietnam is facing a shortage of nearly 2,000 workers, primarily skilled technical staff and equipment operators.
  • Despite the labor gap, the project has achieved over 76% completion, with contractors working in "3 shifts, 4 teams" to meet the late 2026 deadline.
  • The Minister of Construction urged all parties to maintain the schedule, ensure timely payments, and improve working conditions for the on-site workforce.

Construction on Vietnam's ambitious Long Thanh International Airport project is progressing, but a significant labor shortage threatens its timely completion. The project currently requires nearly 2,000 additional personnel, particularly skilled technicians and specialized equipment operators, to meet its demanding schedule.

Despite this challenge, the overall project has reached over 76% completion. Contractors are working around the clock in a "3 shifts, 4 teams" system to accelerate progress and meet the target of opening the airport by the end of 2026. Over 6,800 workers are currently on-site, an increase of more than 6.5% from the previous month. Some units have even brought in over 100 military personnel to bolster the workforce.

The spirit throughout is not to delay the schedule.

โ€” Minister Tran Hong MinhEmphasizing the urgency and importance of meeting the project's timeline.

Minister of Construction Tran Hong Minh led a site inspection on June 13, emphasizing the critical need to adhere to the schedule. He urged all involved parties to meticulously review remaining work volumes and payment documentation. The minister also stressed the importance of supporting and motivating the engineers and workers who are dedicating long hours to the project.

Furthermore, Minh called for a "work-as-you-go" approach to finishing tasks, ensuring synchronization between construction and landscaping. Completed areas must be cleaned, and planting of grass and trees should commence promptly during the rainy season to enhance the project's aesthetic appeal. The minister also requested cooperation with the military for site cleanup, landscape improvement, and tree planting efforts.

Work as you go and finish what you do, ensuring synchronization between construction and landscaping.

โ€” Minister Tran Hong MinhInstructing on the approach to completing project elements and site beautification.
DistantNews Editorial

Originally published by Tuแป•i Trแบป in Vietnamese. Translated, summarized, and contextualized by our editorial team with added local perspective. Read our editorial standards.