MRT Xidong Line construction reaches 31% completion, targets 2032 opening

From Liberty Times · () Chinese

Translated from Chinese, summarized and contextualized by DistantNews.

At a glance

News Official statement Ongoing story
  • Construction on the MRT Xidong Line in New Taipei City has reached 31.23% completion.
  • The project aims for a 2032 completion date, with various construction sites progressing as planned.
  • Mayor Hou Yu-ih emphasized the city's commitment to improving Xizhi's transportation infrastructure.

Construction on the MRT Xidong Line in New Taipei City is advancing, with the main structure now 31.23% complete. Mayor Hou Yu-ih visited a construction site on June 20 to review progress, highlighting the project's commitment to a 2032 completion target.

The MRT Xidong Line is moving towards its goal of completion in 2032.

โ€” Hou Yu-ihNew Taipei City Mayor Hou Yu-ih's statement on the project's timeline.

The project spans 5.56 kilometers, with 4.75 kilometers within New Taipei City and 0.81 kilometers in Taipei City. It will feature six elevated stations and one depot. The main construction began on March 20, 2025. Currently, the Tongxing Road site has finished 118 foundation piles and two pier columns.

The main structure project started on March 20, 2025. The city government team is closely monitoring the construction progress. Currently, the Tongxing Road construction site has successfully completed 118 foundation piles and two pier columns, with an overall project progress of 31.23%.

โ€” Hou Yu-ihNew Taipei City Mayor Hou Yu-ih's update on the construction status.

Other construction areas are also moving forward. The Datong Road site will begin sidewalk reduction and fencing in August, while the Xinwu Road site will start foundation pile construction in September after completing its tail track fencing. Geological surveys for the Shehou depot are underway, with fencing expected by year-end. Taipei City sections will see site preparation and fencing begin in August and September, respectively.

The precast beam yard will start site planning and production line construction in September and is expected to begin precast beam production in November.

โ€” Li Zheng-anNew Taipei City's Department of Rapid Transit Systems Director Li Zheng-an on production schedules.

New Taipei City's Department of Rapid Transit Systems stated that the precast beam yard will begin planning and production setup in September, with beam production starting in November. The project is proceeding on schedule, with all efforts focused on the 2032 completion goal.

The construction of the Xidong Line has fully commenced, with overall progress on schedule, and all efforts are focused on the 2032 completion target.

โ€” Li Zheng-anNew Taipei City's Department of Rapid Transit Systems Director Li Zheng-an's concluding remarks on the project's status.