DistantNews
Support us
National Highway 14 Expansion in Dong Nai Delayed by Power Line Relocation Issues
๐Ÿ‡ป๐Ÿ‡ณ Vietnam /Energy & Infrastructure

National Highway 14 Expansion in Dong Nai Delayed by Power Line Relocation Issues

From Thanh Niรชn · () Vietnamese

Translated from Vietnamese, summarized and contextualized by DistantNews.

At a glance

News Named sources Ongoing story
  • The upgrade and expansion of National Highway 14 in Dong Nai province faces delays due to unaddressed issues with power line relocation.
  • Construction on the Nha Bich bridge, a key part of the project, is proceeding slowly because of the electrical infrastructure.
  • Contractors are urging authorities to expedite the relocation of power poles to avoid further project delays and ensure worker safety.

The upgrade and expansion of National Highway 14, specifically the section between Dong Xoai and Chon Thanh in Dong Nai province, is encountering significant obstacles primarily related to the relocation of existing power lines. This has led to a slowdown in construction, particularly impacting crucial bridge projects.

The Nha Bich bridge, a vital connection between Dong Xoai city and Nha Bich commune, commenced construction on January 15, 2026, with a projected completion in 2026. However, work is currently proceeding at a crawl due to the unresolved issue of moving medium-voltage power lines that run through the project's path. Contractors are expressing frustration, noting that the inability to safely bring in larger equipment hinders progress.

Similarly, the Xa Cat bridge in Nha Bich commune is experiencing delays. The presence of power poles within the construction zone is impeding foundation work and pile driving, raising concerns about potential safety hazards for workers. Representatives from the construction companies involved are appealing to relevant authorities for a swift resolution to the power line issue to keep the project on schedule.

Due to the power line obstruction, which compromises safety during construction, we are unable to deploy larger equipment. If the power lines are not cleared soon, the project risks falling behind schedule.

โ€” Tran Thinh VuongA representative from Dai Phong Infrastructure Construction Joint Stock Company expressed concerns about construction delays caused by power lines.

The Management Board of Investment and Construction Projects of Dong Nai City, the project's investor, has reportedly sent multiple requests to the Dong Nai Power Company (PC Dong Nai) for the relocation. Following a site inspection on May 11 involving PC Dong Nai and local authorities, the Dong Nai Department of Industry and Trade mandated that all necessary power pole relocations within the project's scope be completed by July 30, 2026.

However, PC Dong Nai cited difficulties in finalizing technical plans and allocating funds. They stated that the investor had not yet definitively determined the locations for new poles or the exact boundaries for land clearance. While agreements were reached on the positioning of poles for five other bridges (Suoi Dung, Suoi Dong, Lo Gach, Xa Mat, and Suoi Ngang) and the new road alignment by February 5, 2026, the Nha Bich bridge's pole locations were only handed over on May 14. This ongoing dispute over demarcation and land handover is contributing to the project's delays.

The company requests that relevant authorities expedite the relocation of power lines so that the project can accelerate its progress and be completed on the planned schedule.

โ€” Nguyen Hai ThanhA technical officer from My Phuoc Company, involved in constructing the Xa Cat bridge, voiced the need for prompt action on power line relocation.
DistantNews Editorial

Originally published by Thanh Niรชn in Vietnamese. Translated, summarized, and contextualized by our editorial team with added local perspective. Read our editorial standards.