  • Iarnród Éireann has begun the formal land acquisition process for 206 landowners affected by the proposed DART+ West route.
  • The project aims to provide DART services at least every 10 minutes and expand the network from 50 kilometers to more than 150 kilometers.
  • Transport Minister Darragh O’Brien said the notices would help begin construction next year.

More than 200 landowners along Ireland’s proposed DART+ West route have received notices marking the start of a formal compulsory purchase process.

Iarnród Éireann said 206 directly affected landowners received a Notice to Treat. The statutory notice formally begins the land purchase process and confirms CIÉ’s intention to acquire property interests identified in the Railway Order for the project.

DART+ West will extend services to communities including Ashtown, Pelletstown, Broombridge, Castleknock, Coolmine, Clonsilla, Drumcondra, Leixlip, Maynooth, Hansfield, Dunboyne and M3 Parkway. Iarnród Éireann says the route will provide a DART service at least every 10 minutes.

Advancing the DART+ programme is a major priority for Government, and the issuing of these [CPO] notices will help us commence the construction of DART+ West next year.

· Darragh O’BrienIreland’s transport minister described the land acquisition notices as a step toward starting construction.

The project will electrify and upgrade existing lines, expanding the DART network from 50 kilometers to more than 150 kilometers. It also includes a new station at Spencer Dock and upgrades to Connolly Station.

“Advancing the DART+ programme is a major priority for Government, and the issuing of these [CPO] notices will help us commence the construction of DART+ West next year,” Transport Minister Darragh O’Brien said. Iarnród Éireann Chief Executive Mary Considine called the land acquisition process a significant milestone in delivering the wider programme.

DART+ West will deliver a turn up and go level of rail service, with a new more accessible DART stopping at these communities every 10 minutes.

· Mary ConsidineThe Iarnród Éireann chief executive described the planned service frequency and accessibility.