South Korea faces choice: scenic park or villages for semiconductor power line

From Hankyoreh · () Korean

Translated from Korean and summarized by DistantNews. Read the original for the full story.

At a glance

News Sources not specified Context piece
  • The South Korean government's plan to build a power line from Honam to the Seoul metropolitan area has created a dilemma for the Chungcheongnam-do province, forcing a choice between a provincial park and local villages.
  • The Korea Electric Power Corporation is considering routing the 3.5km power line and associated towers through Daedunsan Provincial Park, which is home to protected species and significant natural beauty, or through several villages in Geumsan.
  • Local residents are divided, with some advocating for the park route to protect their communities and others opposing the park's development, raising concerns about ecological damage and tourism.

South Korea is grappling with a critical infrastructure decision that pits economic development against environmental preservation and community well-being. A government-backed project to construct a major power transmission line, designed to channel electricity from the southern Honam region to the power-hungry Seoul metropolitan area, has landed Chungcheongnam-do province with a stark choice: sacrifice a portion of the scenic Daedunsan Provincial Park or route the line through inhabited villages.

If we clear mountain land for transmission towers, the risk of landslides and forest fires will increase, and it will also disrupt the ecosystem.

โ€” Chungcheongnam-do Forest Resources Research Institute officialExplaining the potential environmental damage from constructing transmission towers in Daedunsan Provincial Park.

The proposed route involves installing 3.5 kilometers of power lines and approximately 7 to 8 transmission towers. The Korea Electric Power Corporation (KEPCO) is weighing two options. One path cuts through Daedunsan Provincial Park, a natural area known for its dramatic rock formations and rich biodiversity, including 9 protected species among its 1,648 cataloged flora and fauna. This route, however, risks damaging the ecosystem and diminishing the park's tourism appeal.

The alternative is to run the transmission line through several villages in Geumsan's Jinsan-myeon. Residents in these communities are strongly opposed to this option, arguing that the line would disrupt their lives and negatively impact their living environment. A committee representing residents stated that a preference survey indicated that the living environment was scored higher than the natural environment, implying that areas where people live are less suitable for such infrastructure.

In the preference survey, the living environment scored higher than the natural environment. This means that areas where people live are not suitable (for the transmission line).

โ€” Park Beom-seok, head of the Geumsan County Transmission Line Avoidance CommitteeExplaining the residents' stance against routing the power line through villages.

This decision has sparked inter-regional conflict. If the route through Daedunsan is chosen, the transmission line would be closer to Nonsan, a neighboring city. Officials from Nonsan have expressed opposition, citing potential harm to residents in the Myeokmok-ri area of Beolgok-myeon. KEPCO noted that there are no known precedents for transmission lines being built in natural parks, although exceptions can be made under the Natural Parks Act if deemed unavoidable due to a lack of alternative sites.

If the Daedunsan route is confirmed, residents of Myeokmok-ri in Beolgok-myeon will be harmed.

โ€” Nonsan City officialExpressing concern about the impact on Nonsan residents if the power line goes through the provincial park.

Some critics argue that the entire project, which aims to connect the Honam region to the Seoul metropolitan area, should be reconsidered. They advocate for a principle of "local production for local consumption" (jisan-jiso), suggesting that generating electricity closer to where it is needed would minimize the impact on specific regions. This approach, they contend, would prevent situations where one area must bear the burden for the benefit of another.

There are no known cases of transmission lines being built in natural parks.

โ€” KEPCO officialCommenting on the precedent of constructing power lines in natural parks.