Accelerated pace of work on the A7 Motorway. CNAIR: 'The objective is for 397 km to be open to traffic this year'
Translated from Romanian, summarized and contextualized by DistantNews.
At a glance
- Construction on Romania's A7 Motorway (Autostrada Moldovei) is progressing rapidly, with significant work on a railway overpass near Cleja.
- The project aims for 397 kilometers of continuous highway to be open by the end of 2026, connecting Bucharest to Paศcani.
- Two sections between Adjud and Bacฤu, totaling over 60 kilometers, are nearing completion with over 95% physical progress on one lot.
Work on Romania's A7 Motorway, also known as Autostrada Moldovei, is advancing at a swift pace, according to Cristian Pistol, the Director General of the National Company for Road Infrastructure Administration (CNAIR). A key focus of the ongoing construction is the overpass crossing the railway line at Cleja in Bacฤu County, where the structural framework is currently being built.
The overpass, located at kilometer 83+548 and measuring 1,215 meters in length, involves the installation of beams, concrete pouring for drainage channels, and the construction of the deck slab across multiple spans. Pistol shared an update on Facebook, noting the "good progress" on this critical section of the A7.
On the 47-kilometer stretch between Adjud and Bacฤu, the Romanian constructor UMB Spedition has mobilized approximately 1,900 workers and 400 pieces of equipment. Preparatory work, including drainage ditches, parking areas, and safety barriers, is nearing completion on the Adjud-Rฤcฤciuni segment.
The objective is that this year it will be possible to travel on 397 kilometers of highway, from Bucharest to Paศcani.
Progress on the A7 Focศani-Bacฤu section is particularly strong. Lot 2, Domneศti Tรขrg to Rฤcฤciuni, has achieved over 95% physical completion. Lot 3, Rฤcฤciuni to Bacฤu, is approximately 80% complete. These two lots, spanning over 60 kilometers, represent an investment of approximately 4.18 billion lei (excluding VAT) and are financed through the National Recovery and Resilience Plan (PNRR).
Pistol's ambitious goal is to have 397 kilometers of continuous highway operational by the end of 2026. This route would link Bucharest to Paศcani, comprising 62 km of the A3 Motorway (Bucharest-Ploieศti), 319 km of the A7 Motorway (Ploieศti-Paศcani), and the 16 km Bacฤu Bypass.
Autostrada Moldovei (#A7): good progress of the works at the overpass over the railway line at Cleja, Bacฤu County. In this stage, beams are being installed, work is being done on concreting the ditches and pouring the deck slab on several spans.
Originally published by Adevฤrul in Romanian. Translated, summarized, and contextualized by our editorial team with added local perspective. Read our editorial standards.