ANDE nearing completion of Asunción underground cabling project
Translated from Spanish, summarized and contextualized by DistantNews.
At a glance
- ANDE reports a 70% completion rate for underground cabling work on Benjamín Constant street in Asunción.
- The project, costing G. 8.665 million, aims to remove overhead cables and is scheduled for completion in November 2026.
- This initiative is the third phase of micro-center renovations, following similar projects on Palma and Presidente Franco streets.
The National Electricity Administration (ANDE) has achieved a 70% completion rate for its underground cabling project on Benjamín Constant street in Asunción. The state-funded initiative, with an investment of G. 8.665 million, is on track for a November 2026 completion date, promising to clear the historic city center of unsightly overhead wires.
The project, which demands a state investment of G. 8,665 million, according to forecasts, will be delivered in November 2026 in the center of Asunción.
Currently, work is progressing between Alberdi and 14 de Mayo streets. ANDE President Ing. Miguel Báez recently conducted a technical site inspection alongside Renato Maas, coordinator for the "Asu 500 Años" project from the First Lady's Office. This effort is part of the "Centro Brilla – Benjamín Constant" plan, financed entirely by the state-owned company through a national public tender.
The tasks are part of the "Centro Brilla – Benjamín Constant" plan, financed entirely with own resources of the state company, through National Public Tender No. 1743/2023.
The project involves installing 2,935 meters of underground copper cable and 55 high-efficiency LED streetlights. It also includes the construction of 262 manholes and the laying of ducts for medium voltage, low voltage, and fiber optic cables. This marks the third phase of micro-center renovations, with previous stages on "Palma Brilla" and "Centro Brilla - Presidente Franco" facing public complaints regarding delays and street closures.
The deadline set by the authorities is November 2026, the date on which the reference artery must be completely cleared of overhead wiring and with new protective electrical infrastructure.
The inspection followed a working meeting with the First Lady, Leticia Ocampos, where ANDE presented its project timelines and finances. The discussion also touched upon other urban revitalization initiatives, including the Palmear Fair, Teko Renda, and the Urban Resilience program, all aimed at reorganizing the capital's public spaces.
The works include the installation of 2,935 meters of underground copper cable and the assembly of 55 high-efficiency LED luminaires, to reinforce the public lighting of the area.
Originally published by ABC Color in Spanish. Translated, summarized, and contextualized by our editorial team with added local perspective. Read our editorial standards.