DistantNews
Support us
Quang Ngai Construction Department Issues Ultimatum Over Delayed Landslide Project
๐Ÿ‡ป๐Ÿ‡ณ Vietnam /Disasters & Emergencies

Quang Ngai Construction Department Issues Ultimatum Over Delayed Landslide Project

From Thanh Niรชn · () Vietnamese

Translated from Vietnamese, summarized and contextualized by DistantNews.

At a glance

News Sources not specified Ongoing story
  • A landslide mitigation project in Quang Ngai, Vietnam, is significantly behind schedule, with only 50% of the work completed.
  • The Department of Construction has issued an ultimatum to the contractor, demanding accelerated progress.
  • The contractor must mobilize more resources and work around the clock to meet the July 30 deadline.

A critical landslide mitigation project on the DT.624B route in Quang Ngai province, Vietnam, is facing significant delays, prompting an ultimatum from the provincial Department of Construction. Despite being over halfway through its planned construction period, the project has only achieved approximately 50% of its intended workload.

Mai Van Ha, Deputy Director of the Quang Ngai Department of Construction, stated that the department issued a formal notice to the contractor, design consultant, and supervision consultant. The notice demands an urgent acceleration of work on the project, which aims to repair negative slope erosion, the roadbed, and the road surface at Km14+500 in Dinh Cuong commune.

The contractor, Thanh Dat Construction Co., Ltd., has been instructed to maximize personnel and equipment deployment. They are to implement multiple construction fronts simultaneously, working extended hours and shifts to compensate for the delays. The project must be completed by the revised deadline of July 30.

the department has just issued a written request asking the contractor, design consultant, and supervision consultant to urgently speed up the progress of the landslide mitigation construction project for negative slopes, roadbeds, and road surfaces at Km14+500 on the DT.624B route through Dinh Cuong commune.

โ€” Mai Van HaDeputy Director of the Quang Ngai Department of Construction, explaining the department's action due to project delays.

The Department of Construction also emphasized the need to promptly address the bored pile and retaining wall components to prevent further erosion and ensure the safety of the road and nearby residential areas. The contractor must strictly adhere to labor safety, environmental protection, and traffic safety measures, particularly during nighttime operations, with adequate barriers, warning lights, and signage.

As of June 12, the actual work completed on-site was valued at over 8.6 billion Vietnamese dong, representing just over 50.2% of the 17.2 billion dong contract. The design consultant, Thien Phuc Construction Consultancy Co., Ltd., is required to maintain on-site personnel to address technical issues, while Bรฌnh Minh General Consulting Co., Ltd. (supervision) and Tam Anh ATP Co., Ltd. (project management) must increase site inspections and monitor progress and quality.

mobilize maximum personnel, machinery, and equipment; organize multiple construction fronts simultaneously in a rolling manner, making full use of favorable weather to increase shifts, increase teams, compensate for the delayed volume, and ensure the completion of the entire project before July 30 as planned.

โ€” Department of ConstructionInstructions given to the contractor, Thanh Dat Construction Co., Ltd., to accelerate the project.
DistantNews Editorial

Originally published by Thanh Niรชn in Vietnamese. Translated, summarized, and contextualized by our editorial team with added local perspective. Read our editorial standards.