  • Lâm Đồng province is struggling to resolve issues for 306 non-budgetary projects, with limited progress despite task force efforts.
  • Key obstacles include zoning conflicts, land forestation issues, and overlaps with mineral exploration plans.
  • Many projects face procedural delays, land lease complexities, and legal violations, with some projects facing potential land revocation.

Thanh Niên reports on the persistent challenges faced by Lâm Đồng province in addressing difficulties for 306 non-budgetary projects. Despite the establishment of six task forces led by deputy provincial chairpersons, the results have been limited, with many projects entangled in complex and persistent issues. This situation highlights a significant bottleneck in the province's development and investment landscape.

The article details a variety of reasons behind these stalled projects. A substantial number are bogged down by zoning conflicts (41 projects), while others face hurdles related to forest land leasing and conversion (10 projects). Compounding these issues, 45 projects are complicated by overlaps with mineral exploration zones, such as titanium and bauxite. Furthermore, procedural delays in investment processes, including bidding and adjustments to timelines, affect 32 projects. An additional 34 projects grapple with difficulties in land lease arrangements, specifically the transition from long-term leases to annual payments.

Perhaps most concerning is the revelation that 33 projects are stalled due to prior legal violations, including land and construction law infringements identified during inspections. The complexity is further amplified as 36 projects face multiple overlapping issues. The report also notes common problems like lack of access roads, land clearance difficulties, and insufficient financial capacity of investors. The province's proposed solutions, such as delegating detailed zoning approvals to local authorities and reviewing legal frameworks for projects with violations, indicate a recognition of the need for more streamlined and decisive action. However, the slow pace of resolution suggests that overcoming these deep-seated issues will require sustained effort and effective coordination between provincial and central authorities.