DistantNews
Support us
๐Ÿ‡ณ๐Ÿ‡ต Nepal /Energy & Infrastructure

Three years on, Narayani iconic bridge project yet to take shape

From Kathmandu Post · () English

Summarized and contextualized by DistantNews.

At a glance

News Named sources Ongoing story
  • Construction on Nepal's Narayani iconic bridge, intended to connect Narayangarh and Gaindakot, has seen minimal progress three years after the contract was awarded.
  • Delays in design approval, which took over a year longer than stipulated, have significantly impacted the construction timeline.
  • Commuters express concern over the slow pace of work, highlighting the aging existing bridge's frequent traffic issues and potential structural concerns.

Physical progress on Nepal's much-anticipated Narayani iconic bridge remains minimal, with only foundation work underway, despite a contract awarded three years ago. The project, designed to link Narayangarh and Gaindakot, has been plagued by delays, primarily stemming from repeated design revisions that postponed approval for over a year.

Santosh Bhandari, site engineer at the Division Road Office in Bharatpur, explained that the "design approval was delayed by around 16 months due to modifications," directly affecting construction. The contract with Tundi Construction was signed on June 2, 2023, requiring design completion within one year and construction within the subsequent three. However, design approval was only granted in November last year, significantly behind schedule.

The design approval was delayed by around 16 months due to modifications. That delay has directly affected construction progress.

โ€” Santosh BhandariThe site engineer explains the primary reason for the project's slow progress.

Commuters like Gita Paudel, who frequently crosses the existing Narayani bridge, voice frustration over the slow pace. "I saw the prime minister and ministers lay the foundation stone, but the work appears very slow," she said. The current bridge often experiences vibrations under heavy traffic and congestion, raising concerns about its longevity as the new project lags.

Construction of the bridge's two main towers has yet to commence. While concrete testing for the foundation pile on the Narayanghat side is complete, load testing is pending. Work is currently focused on the abutment foundation, with two of the eight required 35-meter deep piles finished. Tower construction is not expected to begin until after the monsoon season, further pushing back the project's completion.

I saw the prime minister and ministers lay the foundation stone, but the work appears very slow. I hope the new bridge is completed before anything happens to the old one.

โ€” Gita PaudelA commuter expresses concern over the slow pace of construction and the condition of the existing bridge.
DistantNews Editorial

Originally published by Kathmandu Post. Summarized and contextualized by our editorial team with added local perspective. Read our editorial standards.