Cluj Metropolitan Ring Road's Odyssey: 9 years of delays, failed tenders, and a terminated contract
๐Ÿ‡ท๐Ÿ‡ด Romania /Energy & Infrastructure

Cluj Metropolitan Ring Road's Odyssey: 9 years of delays, failed tenders, and a terminated contract

From Adevฤƒrul · () Romanian

Translated from Romanian, summarized and contextualized by DistantNews.

At a glance

News Named sources Ongoing story
  • The Metropolitan Ring Road project in Cluj-Napoca, Romania, faces significant delays, with 9 years passed since the municipality took over the project.
  • Two main tender bids failed, a contract awarded in 2025 was terminated after a year, and the project is now back to tender.
  • Only a small 2-km section is currently under construction, while the feasibility study itself took four times longer than initially planned.

Nine years after the Cluj-Napoca City Hall took over the Metropolitan Ring Road project from the Ministry of Transport, the ambitious infrastructure plan remains largely stalled, plagued by repeated failures and delays. The project, intended to alleviate traffic congestion in the city and surrounding areas, has seen its feasibility study take four times longer than scheduled, two major tender bids collapse, and a contract terminated after only a year.

The initial feasibility study, begun in 2018, was only completed in 2022, four years behind schedule. The approved study outlined a massive undertaking: 42.13 kilometers of ring road, 32.33 kilometers of connecting roads, 20 intersections, 156 structures, and five tunnels, with an estimated cost exceeding 6 billion lei (excluding VAT) plus over 1.35 billion lei for expropriations.

In August 2023, the city managed to sign a contract for the first section, a 22.4 million euro deal for the segment between Cluj-Napoca and Floreศ™ti, involving road widening and infrastructure for public transport and a new hospital. However, the main part of the project, encompassing Tronsoanele 2 and 3, faced its first tender failure in 2023 when no construction companies submitted bids. A second attempt in late 2023 also failed, despite attracting a single bidder, leading to renewed criticism of the local administration's competence.

The major failure of the project for the Cluj-Napoca Metropolitan Ring Road is the bill for an incompetent administration, and the citizens of Cluj will bear the cost.

โ€” Horaศ›iu CosmaCurrent Secretary of State in the Ministry of Transport, criticizing the local administration's handling of the project.