Jakarta LRT Velodrome-Manggarai Route Set to Open August 26 After 97.99% Construction Completion

From Republika · () Indonesian

Translated from Indonesian, summarized and contextualized by DistantNews.

At a glance

News Named sources New plan
  • The operational readiness of the Jakarta LRT's Velodrome-Manggarai route is nearing completion, with construction at 97.99% as of late July 2026.
  • The new 12.2 km route will connect 11 stations, extending the LRT's reach and integrating with other public transport modes like Transjakarta and KRL Commuter Line.
  • The line is slated to begin operations on August 26, 2026, aiming to reduce travel time to approximately 28 minutes from Kelapa Gading to Manggarai and boost daily ridership.

Jakarta's Light Rail Transit (LRT) is on the cusp of expanding its network with the Velodrome-Manggarai route, part of Phase 1B, nearing full operational status. Construction has reached an impressive 97.99% completion as of the final week of July 2026, signaling a near-ready state for public use.

Safety is the top priority in every construction and operation of transport infrastructure. Together with DJKA, we are carrying out each testing phase gradually and comprehensively to ensure all systems are ready for operation.

โ€” Robert SarjakaDirector of Technical and Development at Jakpro, emphasizing safety protocols during the final testing phase.

The new 12.2-kilometer segment will link 11 stations, significantly broadening the LRT's service area. This extension is designed not just to add capacity but to enhance connectivity across the capital. Key stations like Rawamangun, Pramuka, Matraman, and Proklamasi will offer seamless integration with the Transjakarta bus system. Crucially, the Manggarai station is positioned as a major transit hub, connecting with the KRL Commuter Line, Airport Train, and Transjakarta, solidifying its role in Jakarta's public transport ecosystem.

PT Jakarta Propertindo (Jakpro), the developer, is working closely with the Directorate General of Railways (DJKA) of the Ministry of Transportation to finalize all safety and operational checks. This includes rigorous testing of infrastructure, signaling, telecommunications, and electrical systems. "Safety is the top priority in every construction and operation of transport infrastructure," stated Robert Sarjaka, Jakpro's Director of Technical and Development, emphasizing the comprehensive testing phases.

All testing stages are carried out gradually, systematically, and comprehensively to ensure every component can function in an integrated manner.

โ€” Allan TandionoDirector General of Railways at the Ministry of Transportation, describing the rigorous testing process.

The official inauguration is planned for August 26, 2026. Once operational, the Velodrome-Manggarai line is expected to cut travel time significantly, with journeys from Kelapa Gading to Manggarai estimated at around 28 minutes. Jakpro anticipates a substantial increase in daily ridership, projecting between 60,000 and 80,000 passengers. This boost is hoped to encourage a shift from private vehicles, thereby alleviating traffic congestion and reducing transport-related emissions.

This testing is also carried out to meet the aspects of safety, reliability, and service quality before being used by the public.

โ€” Allan TandionoDirector General of Railways at the Ministry of Transportation, explaining the purpose of the system testing.